HY8:AOP Stream Simulation: Difference between revisions
No edit summary |
|||
Line 5: | Line 5: | ||
HY-8 will only perform this analysis on crossings with one culvert. | HY-8 will only perform this analysis on crossings with one culvert. | ||
The HY-8 AOP process is defined in HEC 26. A flowchart outlining the method is given in the following illustration. | |||
[[Image:AopFlowChart.jpg]] | |||
The AOP Stream Simulation Dialog has 4 steps in a wizard format: | The AOP Stream Simulation Dialog has 4 steps in a wizard format: |
Revision as of 18:07, 26 June 2014
AOP Stream Simulation
Overview
HY-8 will determine if the culvert is more of a barrier than the immediate upstream and downstream channels. The user will need to determine the lowest flow to allow fish passage, the highest flow to allow fish passage, the peak flow for culvert embedment stability, the cross-section geometry upstream and downstream of the culvert, know the stability of the streambed, and enter the gradations of the streambed upstream and downstream of the culvert crossing.
HY-8 will only perform this analysis on crossings with one culvert.
The HY-8 AOP process is defined in HEC 26. A flowchart outlining the method is given in the following illustration.
The AOP Stream Simulation Dialog has 4 steps in a wizard format:
- Input Reach Data where you enter the flows, channel geometry, and streambed stability
- Gradations where you enter the gradations in the streambed and within the culvert
- Align and Size Culvert where you can change the culvert barrel properties
- Results Table Where you can see most of the variables used to perform these calculations. Use this page to verify that your results are reasonable.
The main AOP Stream Simulation dialog has the steps listed on the left, the selected step data on the right, and navigation buttons along the bottom. You can navigate the steps by clicking on the list or the Next, Back buttons. You can also shift to the Crossing Input Dialog, the Crossing Result Dialog, or the Energy Dissipation Dialog by clicking on the buttons along the bottom.
Limitations
HY-8 will compare the velocity and depth from the culvert that were computed using direct step against the velocity and depth in the cross-sections that were computed using manning's equation.
Due to the way that the HY-8 engine is setup, it can be difficult for HY-8 to accurately compute low flows. While we are working to improve HY-8 to handle this condition better, a work around is to set the discharge in the Culvert Crossing Input Data Dialog to User Defined, and setting the number of discharges to a number higher than 10. It doesn't matter what the discharges are, just the total number of discharges.