The ''GSSHA Calibration Output'' dialog can appear after a GSSHA run.
 
The parameter list spreadsheet has a row for each key value, showing the following information for each entry:
*''Parameter'' – Displays the name of the parameter and the units used by the parameter (if any).
*''Key'' – The key value ID associated with the parameter.
*''Run 1 Start Value'' – The initial value for the parameter at the beginning of the first run.
*''Run 1 Optimized Value'' – The optimized value after the first run.
 
Additional run columns will appear with multiple runs.
 
At the bottom of the spreadsheet are entries for the following:
*''Starting Objective Value'' – The objective value before a specific run.
*''Optimized Objective Value'' – The optimized objective value obtained after a specific run.
 
At the bottom of each optimized run is a checkbox:
*''Select an Optimization'' – Turn on the checkbox to select that optimized run for importing into the project.
 
At the bottom of the dialog are the following options:
*''Run simulation with optimized values'' – Turn on to run the simulation using the selected optimized values.
*''Replace key values in project with optimized values'' – Turn on to replace the original key values in the project with the optimized key values. If this option is turned on, a ''Save GSSHA Project FIle'' dialog will appear when '''OK''' is clicked, allowing the original project to be overwritten, or allowing a new project to be saved under a new name.
*'''OK''' – Save all changes and close the ''GSSHA Calibration Output'' dialog.
*'''Cancel''' – Discard all changes and close the ''GSSHA Calibration Output'' dialog.
 
 
{{GSSHA Wiki}}
{{WMSMain}}
 
[[Category:GSSHA Dialogs|G]]

Latest revision as of 19:15, 21 May 2019

GSSHA Calibration Output dialog

The GSSHA Calibration Output dialog can appear after a GSSHA run.

The parameter list spreadsheet has a row for each key value, showing the following information for each entry:

  • Parameter – Displays the name of the parameter and the units used by the parameter (if any).
  • Key – The key value ID associated with the parameter.
  • Run 1 Start Value – The initial value for the parameter at the beginning of the first run.
  • Run 1 Optimized Value – The optimized value after the first run.

Additional run columns will appear with multiple runs.

At the bottom of the spreadsheet are entries for the following:

  • Starting Objective Value – The objective value before a specific run.
  • Optimized Objective Value – The optimized objective value obtained after a specific run.

At the bottom of each optimized run is a checkbox:

  • Select an Optimization – Turn on the checkbox to select that optimized run for importing into the project.

At the bottom of the dialog are the following options:

  • Run simulation with optimized values – Turn on to run the simulation using the selected optimized values.
  • Replace key values in project with optimized values – Turn on to replace the original key values in the project with the optimized key values. If this option is turned on, a Save GSSHA Project FIle dialog will appear when OK is clicked, allowing the original project to be overwritten, or allowing a new project to be saved under a new name.
  • OK – Save all changes and close the GSSHA Calibration Output dialog.
  • Cancel – Discard all changes and close the GSSHA Calibration Output dialog.